Submitted application are reviewed for completeness.
Technical screening is performed, followed by site visits and approval to install your facilities. Site visit and cost analysis are also performed.
ACE conducts design engineering and construction activities for the interconnection of your facility.
System installed by Developers. System should not be installed prior to receiving Approval to Install letter.
System is inspected by customer and ACE.
Subscriber is issued an Authorization to Operate letter. (System should not be turned on until ATO is received.)
ACE is accepting Interconnection Applications for the pilot program by email at CommunitySolarNJ@exeloncorp.com. All Interconnection Applications will be processed in accordance with New Jersey Administrative Code 14:8-5.
The technological, legal, and regulatory considerations that apply to the interconnection of solar generation and other distributed energy resources are complex and constantly evolving. To the best of Atlantic City Electric's knowledge, the information presented on the Company's Hosting Capacity Map is accurate in all material aspects. However, Atlantic City Electric and their affiliates cannot guarantee the accuracy of the information found on this map, and any such information is subject to immediate change at any time. Please seek appropriate technical, operational, financial, and legal advice before proceeding.
Atlantic City Electric cannot guarantee nor reserve capacity in the queue for community solar projects. If and when the New Jersey Board of Public Utilities ("BPU") approves a community solar project, any such project will need to be studied at that time to determine the feasibility of interconnection. Accordingly, any interconnection study conducted prior to BPU approval of a proposed community solar project shall not serve to reserve or guarantee capacity for the proposed project, and a post-approval interconnection study shall be required for any such project, the costs of which shall be borne by the customer-generator.
By signing this application, the customer-generator acknowledges the foregoing, and further agrees that Atlantic City Electric Company shall not bear any responsibility for the costs of any interconnection study, nor the cost of any upgrades required for any proposed interconnection, and that any such costs shall be borne by the customer-generator.